Working on the Petersburg baseball fields

Work Add comments

Since Monday i have been working on the baseball fields. We’re working on finishing up the fencing on the yellow field and would have been done fencing it today but suddenly the concrete we needed to get the foundations for the dugouts on the blue field was available so we got them poured. Tomorrow we’ll get the framing for the foundations of the yellow field’s dugouts completed and ideally finish the fencing too. Then Friday morning we’ll get those foundations poured and probably work on installing bollards to keep vehicles off of the fields. Next week the focus will be construction of the four dugouts.